Sheet 3: Typical Costs

System cost estimates, retrofit situation
Item Small System (1 cubic meter per day) four bedrooms Large System (4 cubic meter per day) 16 bedrooms
System cost at site $20,836.00 $42,848.00
Gravel foundation $450.00 $850.00
Sewage connection $450.00 $900.00
Water recycled to toilets $250.00 $2,500.00
Water recycled to laundry $220.00 $350.00
Weater heater for laundry n/a $1,400.00
Water disposal piping budget $910.00 $1,400.00
Recirculation piping & valve $350.00 $350.00
Electrical connection $350.00 $850.00
Commissioning labour $400.00 $600.00



Total costs $24,216.00 $52,048.00
Contingency $2,905.92 $6,245.76
Total before taxes $27,121.92 $58,293.76